@@ -8,12 +8,12 @@ It's quite common that I try to setup something, but is needed another setting f
### Sequence ### Sequence
Setting up a **Manufacturing** module require require a keen eye on details, but sometimes not so detailed in order to avoid complications. Setting up a **Manufacturing** module require require a keen eye on details, but sometimes not so detailed in order to avoid complications.
The sequence to setup the module on my testing [axelor ERP](https://erp.33co.de) instance is the following: The sequence to setup the module on my testing [axelor ERP](https://erp.33co.de) instance is the following:
1 - Setup Country, City, Company information 1. Setup Country, City, Company information
2 - Create workshop, in [Kartano Tech Oy](https://code.33co.de/ehofmann/ERP-samk/src/branch/master/02Process.md) case is the PCB Workshop, Metal Workshop and Assembly Workshop 2. - Create workshop, in [Kartano Tech Oy](https://code.33co.de/ehofmann/ERP-samk/src/branch/master/02Process.md) case is the PCB Workshop, Metal Workshop and Assembly Workshop
3 - Add cancel reasons, during setup I do not know what is the need of such *Cancel Reasons*, I considered as issues in production that could cancel an order 3. Add cancel reasons, during setup I do not know what is the need of such *Cancel Reasons*, I considered as issues in production that could cancel an order
4 - Product approvals, in this item I created inspection step that will approve the product, to be validated at the end. 4. Product approvals, in this item I created inspection step that will approve the product, to be validated at the end.
5 - Machine types. In this case I added twelve type of machines that are necessary to create PCB *"Printed Circuit Boards"* 5. Machine types. In this case I added twelve type of machines that are necessary to create PCB *"Printed Circuit Boards"*
6 - Machines. Here I added the machine that is producing according each manufacturing step. Each machine belong to a *Machine Type* group. 6. Machines. Here I added the machine that is producing according each manufacturing step. Each machine belong to a *Machine Type* group.
7 - Work Centers. Here machines are grouped in order to produce the product, also capacity and costing settings are defined. I will need to return to this settings after adding products to the system, as this information is necessary to define the process cost. 7. Work Centers. Here machines are grouped in order to produce the product, also capacity and costing settings are defined. I will need to return to this settings after adding products to the system, as this information is necessary to define the process cost.